Construction

Check our construction timeline regularly to stay up-to-date on the creation of our contemporary student apartments near SU! Contact our leasing team today for more information.

  • 2025
    October

    Roofing Dry-In

    Begin Roofing Dry-In of the first half of the building structure. Continue Wood and Metal Framing throughout all levels. Begin the installation of unit windows.

  • 2025
    November

    Exterior Façade Installation

    Begin installing the exterior façade. Mechanical, Electrical, Plumbing and Fire Sprinkler systems continue to be installed prior to insulation and drywall. MEP Rough Ins and Finishes will sequence from the top floor down, working our way out of the building. Insulation and Drywall to follow.

  • 2025
    December

    Building Is Topped Out

    The Building reaches Topping Out which means we are structurally complete! Roofing to closely follow leaving a fully dried in structure. Elevators Begin Installation.

  • 2026
    January

    Drywall, Cabinets, & Painting Next Phase

    Drywall Continues followed by Interior cabinets, trim, doors and painting.

  • 2026
    February

    Interior Construction Continues

    Continue construction of interiors by floor.

  • 2026
    March

    Flooring, Tile, & Backsplash Begins

    Interior Flooring, Tile and Backsplash begin. Tower Crane and Buckhoist are removed. Exterior building façade is continuing.

  • 2026
    April

    Drywall Installation Completed

    Completion of drywall installation. The crews will continue painting, installing cabinets, countertops, plumbing & light fixtures.

  • 2026
    May

    Landscaping Begins

    Landscaping and Hardscapes are getting started. Kitchen and Laundry Appliances continue to be installed in the units. Exterior building façade is nearing completion.

  • 2026
    June

    Furniture Installation Begins

    Pool/Spa is being turned on. Courtyard Pavers are installed and amenity spaces begin to come to life. Begin Systems checkout, Final life safety inspections, TCO inspections. Furniture installation begins. Install TV, Internet, WiFi network, security cameras.

  • 2026
    July

    Final Repairs & Touch-Ups

    Crews will continue wrapping up and making final repairs & touch-ups. Community manager and leasing will move and learn all the operational equipment.

  • 2026
    August

    Move-In Month

    Re-Paving of Madison Street. Construction Demobilization and moves-Out. Resident Move-In Month! Quality checks will be completed and residents will begin moving into their brand new apartments on August 21st.